Packaging Factory

Project Brief:
HIGH-PRESSURE PROCESSING

Doing What’s Needed

Project Proponent:    ONESOURCE, ONEHEART, ONEDREAM ASSOCIATION
Mgmt Proj Operator:    COCOWILD PTY LTD.
Pilot Location:    Zamboanga del Sur (A total of 822 MUNICIPALITIES from the 64 coastal provinces shall be covered by this project)
Phase One:    One Municipality from each Province
Other Locations :
Luzon:    Zambales, Catanduanes, Cavite, Batangas

Visayas:    Bohol, Western Samar, Capiz, Leyte

Mindanao:    Camiguin, Davao Oriental, Davao Occidental,
Agusan del Norte,

REVENUE/COST SUMMARY PER PLANT for 1st FIVE YEARS
INTERNAL RATE OF RETURN:    110%
ROI:    502%
Return to Farmers:    PhP 40,541,836.00
HPP Equipment Cost:    PhP 91,745,000.00
Indicative Freight Cost:    PhP 885,000.00
Installation/Commissioning:    PhP 10,080,000.00
Land and Building:    PhP 64,900,000.00
Associated Equipment:    PhP5,900,000.00
Working capital:    PhP16,196,000.00
TOTAL PROJECT COST/PLANT: PhP 189,706,000.00

This project shall service the packaging of chicken for market retail distribution as well as the fruit and vegetable produce from farm e.g., coffee, etc. in order to maintain the freshness and sanitary condition and longevity of shelf life of such products.

TOTAL ESTIMATED PROJECT COST for 12 regions:             PhP 2,276,472,000.00